Project Description
This project included removing the visual screen around the existing (4) cooling towers and replacing them with new structural supports. The cooling towers were repaired and the 18” condenser water supply and return piping was replaced with 24” piping. The project was designed to remove known seismic risks and to lower risk of service disruption. The Central Utility Facility provides steam and cooling 24 hours a day, 365 days a year.
PROJECT TYPE
GENERAL CONTRACTOR
Plumbing, Piping, and Construction, Inc.
Mechanical Engineer
P2S
Contract Amount
$2.1 million